NGCP Advisory
Restored power transmission service in parts of Iligan City and parts of Baloi, Lanao del Norte, 12 August, 11:49AM.
Affected: ILPI, LANECO (M3), and TESDA
Restored Facility: 20MVA Power Transformer (PT)
Reason: the newly installed 20MVA PT at Overton Substation is energized at 10:01AM but tripped at 10:03AM today due the technical problem. Iligan-Maria Cristina Norte and Iligan-ILPI 13.8KV lines were re-energized accordingly at 11:54AM and 11:53AM, respectively.
Via Beth A. Ladaga