NGCP Advisory

Restored power transmission service in parts of Iligan City and parts of Baloi, Lanao del Norte, 12 August, 11:49AM.
Affected: ILPI, LANECO (M3), and TESDA
Restored Facility: 20MVA Power Transformer (PT)
Reason: the newly installed 20MVA PT at Overton Substation is energized at 10:01AM but tripped at 10:03AM today due the technical problem. Iligan-Maria Cristina Norte and Iligan-ILPI 13.8KV lines were re-energized accordingly at 11:54AM and 11:53AM, respectively.
Via Beth A. Ladaga
For God so loved the world, that he gave his only Son (Jesus Christ), that whoever believes in him should not perish but have eternal life. For God did not send his Son into the world to condemn the world, but in order that the world might be saved through him. Whoever believes in him is not condemned, but whoever does not believe is condemned already, because he has not believed in the name of the only Son of God. - John 3:16-18

● ● ● ●