Yes, that's true. That's how shameful it is. Aside from the five (5) NIA grafters who got sued for this mess, the boholanos should blame the following agencies:
1.) The Commission Or Audit (COA), kay dili kamao mo compute og "percentage accomplishment". Ang total project cost is 243Million; ang NIA migasto na og 165Million; apan ang na homan wapa kaabot og katunga (<50%) sa construction. Di ba sayon ra unta computon? 165M over 243M equals 0.679%! So kun migasto na og 165M, dapat almost 70% accomplishment na unta.
2.) The Ombudsman, kay labaw pa sa COA. Wa mag compute mituo lang pod dayon sa taga COA hook line and sinker.
Ang resulta, the five (5) grafters are now as free as the wind blows.