Recent updates on the Panglao Bohol Airport Development Project:
1. Detailed Engineering Design was awarded to PhilJAC, a Filipino and Japanese consulting firm, in December 2008.
2. PhilJAC's survey teams are now at the project site for precise survey for building and other facilities layout preparatory to construction. Other activities for DED are ongoing.
3. About 30 Panglaoanons will be hired to clear the shrubs for one month. This is to complement the work of the survey teams.
4. The relocation site for qualified affected families is also undergoing subdivision survey.
5. PhilJAC has recommended the development of an additional access road leading to the airport terminal (which will become the main access road).
6. DOTC has already transferred 37.5 Million to the Prov'l Gov't as additional funding for payment of lots, improvements, and related activities.
7. Construction work is expected to start by first week of October 2009
8. Estimated time of completion is December 2010